CASE STUDY - Replace Steam Coils In Tallow Tanks (value $21,000)

SITUATION

Large abattoir SE Queensland

TASK

Replace steam coils in tallow storage tanks

ACTIONS

  1. Obtain customers initial requirements
  2. Supply quotation
  3. Determine materials to be used
  4. Work out how task to be carried out
  5. Consult details with customer for approval
  6. Supply customer with timeline for work to be carried out
  7. Remove tanks on weekend
  8. Roll stainless steel pipe in our own machines
  9. Fabricate and install in tank
  10. Install and commission on site
  11. Communicate with customer on progress throughout the job

RESULT