CASE STUDY - V RAM PUMP INSTALLATION (value $240,000)

SITUATION

A large South East Queensland abattoir required installation of a V Ram Pump and associated structures in order to facilitate increased production at the plant.

TASK

Hagan Machinery was commissioned to:

ACTIONS

  1. Prior to quoting, Hagan Machinery liaised closely with abattoir management in order to accurately scope the project and clarify project deliverables.
  2. Gavin Hagan prepared a project plan identifying & allocating internal and external resources (human and material), identifying production milestones & performance indicators and setting timelines for each phase of the pipe and pump installation and commissioning.
  3. The pipe size and grade options were analysed in relation to availability, processing restrictions and cost. On the basis of this needs analysis, suitable materials were sourced.
  4. Gavin liaised closely throughout the operation with the pump supplier so that the installation would facilitate peak performance of the V Ram Pump.
  5. Hagan Machinery negotiated access times and protocols with abattoir management so that factory production was not impeded.
  6. Hagan Machinery sourced skilled contactors in Australia and overseas to implement the induction bending of the large pipes.
  7. As necessary, other expert consultants and contractors were employed to complement the skills of Hagan Machinery's in-house design and production teams. These included structural and mechanical engineers, a drafting contractor, electricians and plant operators
  8. Throughout the project Hagan Machinery deployed regular feedback loops were so that the client remained informed of progress, decisions could be taken quickly and the project milestones met within set timeframes.

RESULT